Entrust Services obtained planning permission in 2021 for a 254-acre solar farm at Ballyroe, near Charleville in County Cork. This project also included a 3.5KM underground electricity grid connection.
Addressing Site Challenges
The site presented various challenges including archaeology, flood risk, and adjacency to a Special Area of Conservation (SAC).
Mitigation Measures and Collaboration
Entrust collaborated closely with the Planning Authority and Public Bodies to devise appropriate mitigation measures to address environmental concerns and ensure no negative impacts prior to the application submission.
During the application process, there was an issue with a new proposed motorway corridor optional route. However, this obstacle was successfully addressed and removed, facilitating the grant of planning permission.
Comprehensive Planning Solutions
Entrust Services provided end-to-end planning solutions, serving as the planning application project manager and offering a range of environmental specialisms both in-house and through expert consultants.
Services Offered
Entrust Services provided a comprehensive range of services, including:
Planning statement & policy analysis
Pre-planning consultation
Environmental impact assessment (EIA) screening
Public consultation & statement of community consultation
Archaeology & cultural heritage assessments
Hydrology & flood risk assessment (FRA)
Landscape and visual impact assessment (LVIA) with photomontages
Zone of theoretical visibility (ZTV) analysis with and without vegetation
Landscaping scheme development
Construction environmental management plan (CEMP)
Appropriate assessments (AA)
Natural impact statements (NIS)
Biodiversity management plans (BMP)
Noise and transport management plan (TMP)
Complete set of planning application drawings
Pre-planning consultation
Archaeology & cultural heritage assessments
Landscape and visual impact assessment (LVIA) with photomontages
Landscaping scheme development
Appropriate assessments (AA)
Biodiversity management plans (BMP)
Noise and transport management plan (TMP)
Planning statement & policy analysis
Environmental impact assessment (EIA) screening
Public consultation & statement of community consultation
Hydrology & flood risk assessment (FRA)
Zone of theoretical visibility (ZTV) analysis with and without vegetation
Construction environmental management plan (CEMP)
Natural impact statements (NIS)
Complete set of planning application drawings
Conclusion
Entrust’s comprehensive planning application solution, coupled with our collaborative approach, played a pivotal role in securing the successful approval of the Ballyroe solar farm. This achievement underscores our unwavering commitment to sustainable development and environmental stewardship.Ready to kickstart your sustainable project?